November 2008
Column -

AutomatedBuildings.com

BTL Mark: Resolve interoperability issues & increase buyer confidence
BACnet Testing Laboratories

(Click Message to Learn More)


Data Center Building Automation

In many ways data centers come closest to blurring the line between commercial and industrial controls in our industry.

 Paul Ehrlich & Ira Goldschmidt
Building Intelligence Group

As published
 

November Issue - Column 

Now that the dot.com bubble has taken on the dimness of history it is interesting to reflect on how mission critical buildings have influenced building automation system design. Looking back at the crazy days of the late 90’s we may recall that it was not a good time to put quality thinking into how best to control a mission critical facility. Many projects struggled with both short schedules (and we know what design/construction aspect suffers the most when this happens) and overly-ambitious uptime criteria (everyone was vying for bragging rights on the greatest “number of 9’s”). Fortunately, data centers have continued to be built and generally have had more realistic approaches to balancing cost and quality and now energy efficiency.

Articles
Interviews
Releases
New Products
Reviews
Blogs
Sponsors
Archives
Past Issues
AutomatedBuildings.com

ABB

What’s interesting about mission critical facility design is that it forces the controls designer to ponder questions about a specialized BAS design (just like healthcare and labs, but in a very different manner) than for the typical commercial facility. In many ways data centers come closest to blurring the line between commercial and industrial controls in our industry. So what are the controls issues that make mission critical facilities so unique? Simply put the requirement for virtually no HVAC down-time requires systems that are redundant and failsafe. But what does this really mean to the controls designer? While we might expect to find the answer to these questions from industry groups such as the Uptime Institute that defines criteria for “Tier 1, 2, etc.” the issues of controls and automation are not clearly addressed.

Redundancy seems like a straightforward concept to mechanical design, but when applied to controls it gets much more complicated. For example we know that mechanically an N+1 chiller plant has one more chiller installed than is needed to meet the load. But what controls redundancy is required for an N+1 design? Here’s some things to consider:

  • Shouldn’t each chiller and its associated pumps, cooling tower, etc., be controlled by a dedicated BAS controller? On the other hand, what if each chiller system require so many points of control that more than one controller is required – if so, does the required controller-to-controller communications degrade redundancy?

  • Since the chiller plant typically feeds a common, variable-flow chilled water loop how many differential pressure sensors should there be and to which of the above controllers should they be connected? For example, if there is only one sensor and the controller to which it is connected fails then so much for mechanical redundancy, but how many sensors are needed?

  • Should the controllers contain redundant common control sequences? For example, the common chilled water pump VFD/pressure control sequence - what if the controller in which that sequence resides fails? Shouldn’t there be a redundant version of that control sequence in more than one controller?

  • Should each of the above controllers be fed by a completely separate UPS-backed power source? If so, how many separate power sources are important for, say, a chiller plant with four chillers?

Failsafe is a design goal that can mean different things to different people. In mission critical design it generally means that when a controls or communications component fails the controlled system should not stop operating (within reason of course). Again, here are some alternatives to consider concerning failsafe:

Controls and BAS design for mission critical facilities requires focus and attention on these many issues as well as the added challenge to attempt to deliver on energy efficiency. In short these can be very satisfying, but challenging projects.


About the Authors

Paul and IraPaul and Ira first worked together on a series of ASHRAE projects including the BACnet committee and Guideline 13 – Specifying DDC Controls. The formation of Building Intelligence Group provided them the ability to work together professionally providing assistance to owners with the planning, design and development of Intelligent Building Systems. Building Intelligence Group provides services for clients worldwide including leading Universities, Corporations, and Developers. More information can be found at www.buildingintelligencegroup.com  We also invite you to contact us directly at Paul@buildingintelligencegroup.com or ira@buildingintelligencegroup.com

footer

Haystack Connect 2019
[Click Banner To Learn More]

[Home Page]  [The Automator]  [About]  [Subscribe ]  [Contact Us]

Events

Want Ads

Our Sponsors

Resources